TBG-KV2-MEP-001MFAR Kuda Villingili (KV2) — Kaafu Atoll, Maldives
Rev 01 · 07 September 2026

MEP Materials

Electrical, HVAC, plumbing, foul drainage, water supply, pool plant and fire — plus the URA approvals this scope triggers.

← All schedules Download .xlsx to quote Rate and quantity cells are left blank for you to complete in the workbook.
D / FIRM — confirmed by the issued drawings A / PROV — assumed design intent, absent from the package ALT — a priced alternative to the row above, not an addition Not scheduled — cannot be priced until the consultant issues it Blank — for you to fill in
SystemElementMaterial / equipmentStatusSpecification / basisUnitApplies toWhy this, for a Maldives resort villaQtySupplier / originUnit rateAmountLead time
1. ELECTRICAL - INCOMING SUPPLY, DISTRIBUTION AND PROTECTION
ElectricalIncoming supplyResort LV network connection, termination and isolation setAA - undrawn: 230/400 V, 3-phase, 4-wire, 50 Hz supply with separate protective conductor. Existing source, spare capacity, earthing arrangement and connection point require confirmation.setAll fourEstablishes the interface with the island power system; no new generator is assumed per villa.
ElectricalVilla submainCopper XLPE insulated, armoured, water-resistant sheathed cableAA - undrawn: 0.6/1 kV; preliminary quotation sizes: 5-core 25 mm² for A09/A12 and 5-core 35 mm² for A10/A11. Final sizes depend on length, grouping, temperature, voltage drop and fault clearance. Lengths unmeasured.mAll fourLong jetty feeders can require substantial upsizing; specify outdoor UV resistance and suitable wet-location construction.
ElectricalBeach-villa feeder ductsHeavy-duty HDPE electrical ducts, bends, draw rope and warning tapeAA - undrawn: preliminary 110 mm ducts, including one spare duct along shared routes; long-radius bends and accessible pulling points. Burial depth and mechanical protection require coordinated design.mA09, A10Replaceable cables and spare ducts reduce future excavation and island delivery disruption.
ElectricalVilla distribution boardFactory-built copper-busbar distribution assemblyAA - undrawn: one per villa; preliminary 63 A incomer/100 A busbar for A09/A12, 80 A/125 A for A10/A11; approximately 24-36 and 36-54 single-pole outgoing ways respectively, with >=25% spare capacity. IEC 61439 assembly; IP54 in a dry service room.setAll fourSpace is needed for relays, metering, controls and future replacement; room area alone does not establish that the board fits.
ElectricalMain protection and meteringElectronic overcurrent protection, earth-leakage relay, core-balance CT, trip release and multifunction meterAA - undrawn: provide both overcurrent and earth-leakage relays; measure A, V and Hz. Enquiry current ceilings are 50.4 A and 64 A per phase for the assumed incomers. Busbars >=125% of incomer; metering CT primary, where used, <=incomer trip. Final settings require coordination.setAll fourThese numerical checks follow the URA SLD guideline, PDF pp. 1-2; selected ratings remain assumptions.
ElectricalMultiple-source switchingFour-pole breakers and interlocked changeover/ATS equipmentAA - undrawn: allow four-pole switching for affected three-phase supplies where generator, utility or other sources interact; establish neutral switching and earthing on the approved SLD. ATS assumed at shared distribution, not each villa.setAll four - shared interfacePrevents unintended source interconnection and addresses URA multiple-source requirements.
ElectricalFinal-circuit protectionIndividual RCBOs and equipment-specific protective devicesAA - undrawn: 30 mA Type A RCBOs as enquiry base; typically 6-10 A lighting, 16-20 A sockets and 16-32 A dedicated equipment circuits. Type F/B where the inverter manufacturer requires it. Breaking capacity selected from fault calculations.noAll fourSeparate circuits limit guest disruption when one outdoor fitting or appliance develops leakage.
ElectricalInternal circuit wiringCopper LSZH insulated singles or sheathed cablesAA - undrawn: preliminary 1.5 mm² lighting, 2.5-4 mm² sockets and 4-6 mm² plant circuits, each with CPC. Match conductor size to installation method and protection; these are quotation sizes.mAll fourStandardising a small cable range simplifies stockholding and repairs.
ElectricalInternal containmentHeavy-duty rigid nonmetallic conduit, trunking, boxes and bushesAA - undrawn: generally 20/25 mm conduit, larger at grouped runs; segregated power and communications pathways. Fire performance appropriate to the adopted building strategy.mAll fourNonmetallic containment avoids rust staining and concealed corrosion.
ElectricalOutdoor connectionsUV-stabilised GRP/polycarbonate junction boxes, glands, lugs and sealsAA - undrawn: IP66 exposed boxes; tested immersion-rated joints only where unavoidable and specifically engineered. Tinned copper lugs, sealed cable entries and corrosion-compatible glands.setAll fourIP66 protects against spray, but does not make a submerged connection acceptable.
ElectricalLocal plant isolationLockable weatherproof isolatorsAA - undrawn: suitably rated double-pole or four-pole isolator at each AC outdoor unit, heater, pump and other maintainable appliance; IP66 outdoors.noAll fourTechnicians can isolate individual equipment without entering occupied guest rooms.
ElectricalSocket outletsShuttered switched sockets and back boxesDD: bedroom outlets appear on elevations; quantities unspecified. A: BS 1363, 13 A outlets; IP66 outdoor accessories, positioned outside prohibited bathroom/pool zones. USB-C charging modules where the operator requests them.noAll fourRobust standard sockets are easier to replace than proprietary universal outlets.
ElectricalMinibar supplyDedicated unswitched socket and labelled circuit connectionDD: minibar shown; electrical details absent. A: one 13 A supply per villa, continuously energised and excluded from key-card shutdown; confirm appliance quantity and ventilation requirements.setAll fourKeeps refrigeration operating while the guest is away.
ElectricalGuest safe provisionBattery provision or concealed power connectionAA - undrawn: assume one battery-operated safe per villa supplied through FF&E; no mains circuit in the base. A powered safe would require a concealed permanent supply to its manufacturer's specification.setAll fourAvoids unnecessary wiring and duplicate purchase of the safe itself.
Electrical
ElectricalProtective earthingMain earth terminal, copper CPCs, earth links and test pointsAA - undrawn: TN-S distribution assumed pending source verification; continuous CPC from shore to each water villa. Preliminary main bonding conductors 16-25 mm², subject to fault and bonding calculations.setAll fourSeawater, piles and incidental metalwork are not substitutes for a designed protective conductor.
ElectricalEquipotential bondingCopper bonding conductors, compatible clamps and accessible linksAA - undrawn: preliminary 4-6 mm² local supplementary bonding where required; bond applicable pool equipment and extraneous conductive parts following the adopted electrical design.mAll fourWet bare-foot environments require reliable fault protection; connections must resist corrosion.
ElectricalLightning protectionConventional air terminals, down conductors, test joints and earth terminationAA - conditional, undrawn: provide only to a completed IEC 62305 risk assessment; preliminary conductor quotation basis 50 mm² copper or approved equivalent. Coordinate separation distances, roofing interfaces and shore earth network.setAll fourExposed lagoon structures require assessment; air terminals alone do not constitute a complete system.
ElectricalShared generation interfaceGenerator/synchronising/ATS extension packageAA - conditional, undrawn: audit existing resort generation before pricing additions. Any new set includes alternator, controller, starting batteries, exhaust, cooling, fuel system, metering and protection; kVA cannot be established from this ID package.setAll four - sharedGeneration capacity is a resort-wide decision, not a villa materials allowance multiplied by room count.
ElectricalSolar generation interfacePV modules, inverter, DC/AC protection and monitoringAA - conditional, undrawn: separate shared infrastructure allowance only if instructed; capacity, roof suitability and generator/PV controls require design. No PV quantity inferred from villa floor area.setAll four - sharedSolar can reduce fuel deliveries, but island-grid compatibility must be engineered.
ElectricalBuggy chargingOEM charger supplies and weatherproof charging outletsAA - conditional, undrawn: base location is the shore-side service depot; allow dedicated 230 V, 16 A circuits for OEM chargers, typically 1-3 kW input each. Confirm battery chemistry and charger duty.setAll four - sharedConcentrates maintenance and charging away from guest decks and lagoon exposure.
ElectricalRoad-vehicle EV chargingManaged Mode 3 charging equipmentAA - conditional, undrawn: only if road EVs are actually proposed; preliminary 7.4 kW, 230 V, 32 A charger with appropriate residual-current/DC-leakage protection and load management.noShared shore facilityA resort buggy charger is not automatically an EV wallbox requirement.
2. ELECTRICAL - LIGHTING, CONTROLS AND COMMUNICATIONS
ElectricalCOB spotlightsAnti-glare LED luminairesDD: 1 W, 3 W and 5 W at 3000 K; 10 W described as white. A: CRI >=90, replaceable driver and suitable wet-zone rating. Exact CCT of "white", beam angles, quantities and dimming compatibility are unresolved.noAll fourConsistent colour and low glare support the guest experience; do not silently substitute 3000 K for the unspecified white fitting.
ElectricalCove lightingDimmable LED tapeDD: 2800 K, approximately 18-62 m per villa; type-specific lengths unavailable. A: 24 V constant-voltage tape, preliminary 9.6 W/m, CRI >=90; output and lengths require the lighting design.mAll fourLower-voltage tape suits concealed coves; long runs need distributed feeds to avoid uneven brightness.
ElectricalLED mountingAnodised aluminium profiles, diffusers, end caps and clipsAA - undrawn: continuous heat-dissipating profile sized for selected tape, typically 15-25 mm wide; accessible terminations and replaceable diffuser.mAll fourControls LED temperature and protects tape from dust and maintenance damage.
ElectricalLED driversConstant-current spotlight drivers and 24 V constant-voltage strip driversAA - undrawn: matched to each luminaire; preliminary strip-driver modules 60-150 W, normally loaded to <=80% of rating. DALI-2 dimming base; remote accessible mounting, with IP rating appropriate to location.noAll fourStandard replaceable drivers reduce downtime and avoid opening finished ceilings for routine repairs.
ElectricalDecorative wall-light connectionsWiring outlets, mounting boxes and connectorsDD: wall lamps shown; quantities unspecified. A: provide concealed connections and suitable earthing/IP provisions; decorative lamp bodies remain coordinated with the separate finishes/FF&E purchase.setAll fourPreserves the ID selection without purchasing the same decorative fitting twice.
ElectricalIlluminated mirror connectionsIsolated electrical outlets and driver access provisionsDD: mirror counts A09/A12: one; A10/A11: three. A: connection voltage and driver arrangement to mirror supplier; 30 mA protected circuit, bathroom-zone compliant location. Mirror bodies excluded here.setAll fourIntegrated mirror electronics need accessible replacement and moisture protection.
ElectricalLighting controlDALI-2 controller, dimmers, relay modules and scene keypadsAA - undrawn: independent bedroom, bathroom, cove and outdoor groups; welcome, reading, night and all-off scenes. Confirm driver compatibility through a sample-room demonstration.setAll fourSmooth low-level dimming matters more than a nominal "dimmable" label.
Electrical
ElectricalDoorbellSELV doorbell/chime and weatherproof push buttonAA - undrawn: one entrance set per villa, 12/24 V supply; integrate do-not-disturb indication if adopted.setAll fourSimple maintainable entrance signalling avoids disturbing neighbouring villas.
ElectricalFibre backboneAll-dielectric outdoor OS2 single-mode fibreAA - undrawn: preliminary 6-12 fibres per villa branch, water-blocked and UV resistant; termination boxes, splice trays, pigtails and patch leads included. Route along the walkway as Section 9.mAll four; especially A11/A12Fibre avoids long copper-link limits and conductive surge paths between shore and villa.
ElectricalVilla network equipmentPoE switch, fibre termination and compact equipment cabinetAA - undrawn: preliminary managed 8-port switch for A09/A12 and 16-port for A10/A11; ventilated accessible dry cabinet. Small UPS where required by the operator's communications strategy.setAll fourLocal PoE supports WiFi, telephone and room controls with common spare equipment.
ElectricalStructured cablingCat 6A cable, outlets and patching accessoriesAA - undrawn: solid-copper LSZH cable indoors; permanent copper links <=90 m. Outdoor sections require suitable cable construction and containment. Quantities await outlet layouts.mAll fourReliable wired backhaul prevents resort WiFi from depending on a chain of wireless repeaters.
ElectricalWiFiManaged ceiling/wall access pointsAA - undrawn: WiFi 6 or compatible operator standard; preliminary one AP for A09/A12 and two for A10/A11, subject to coverage survey and wall construction.noAll fourCoverage must include the bed, bathroom and usable deck without excessive neighbour interference.
ElectricalTelevision serviceIPTV/data outlet, patch lead and power connectionDD: TV counts A09/A10/A11/A12 = 1/3/2/1. A: IPTV over resort LAN assumed; TV bodies remain FF&E. Add coax only if the operator's headend requires it.setAll fourUses the resort backbone and avoids an assumed dish or receiver at every villa.
ElectricalTelephonePoE IP telephone and labelled data outletAA - undrawn: preliminary one handset for A09/A12 and two for A10/A11; connect to resort PBX, with emergency/front-desk dialling. Bathroom handset only if operator-required.noAll fourSupports guest assistance without a separate long analogue cable network.
3. HVAC
HVACSmall-villa AC - baseMatched concealed ducted inverter split systemAA - undrawn: one indoor unit and one air-cooled outdoor unit per villa; preliminary 6-8 kW cooling. Quote at tropical ambient conditions; final selection requires sensible and latent load calculations.setA09, A12Concealed ducted DX cooling suits a luxury bedroom and permits independent villa maintenance.
HVACLarger-villa AC - baseVilla-scale mini-VRF system with concealed indoor unitsAA - undrawn: preliminary 16-24 kW outdoor system; independent bedroom zones, an enclosed living zone if present, and approximately 2-2.5 kW maid-room unit. Final zone count and capacities require plans and heat-load calculations.setA10, A11Several indoor zones share fewer outdoor units, reducing congestion around small service rooms.
HVACLarger-villa AC - substitutionSeparate one-to-one ducted inverter splitsALTALT - undrawn: replaces the larger-villa mini-VRF package above; separate matched systems for each conditioned zone, selected to the same calculated loads.setA10, A11More outdoor space is needed, but a compressor failure can be confined to one zone.
HVACOutdoor-unit marine packageFactory-treated coils, coated chassis and corrosion-resistant fastenersAA - undrawn: factory coastal treatment covering coils, edges and casing; documented suitability for the actual salt exposure, protected electronics and accessible freshwater wash-down.setAll fourA generic "blue-fin" description alone does not establish resistance to severe lagoon exposure.
HVACOutdoor mountingEquipment rails, vibration isolators and compatible fixing hardwareAA - undrawn: corrosion-resistant supports, restrained elastomer/spring isolation as selected, manufacturer airflow and service clearances. Locate outside enclosed MEP rooms unless engineered ventilation supports the heat rejection.setAll fourPrevents hot-air recirculation, bedroom vibration and premature corrosion.
HVACRefrigerant pipeworkRefrigeration-grade dehydrated copper tube and fittingsAA - undrawn: EN 12735-1 tube; preliminary small-system liquid OD 6.35-9.52 mm and gas OD 12.7-19.05 mm. VRF branches, diameters and equivalent lengths strictly to selected manufacturer.mAll fourCorrect tube quality and controlled joints are essential where refrigerant repairs require island mobilisation.
HVACRefrigerant and commissioning consumablesOEM refrigerant, dry nitrogen and approved jointing consumablesAA - undrawn: R32-based equipment is an enquiry option, subject to actual product availability, charge limits and room-volume safety assessment. Charge only by the selected system's schedule.kgAll fourAvoids mixing refrigerants or assuming an unrestricted charge in small sleeping rooms.
HVACRefrigerant insulationClosed-cell elastomeric insulation with sealed vapour barrierAA - undrawn: preliminary 19 mm indoors and 25 mm outdoors, increased where condensation calculation requires; all joints vapour-sealed, with UV-resistant external jacketing.mAll fourTropical humidity makes gaps in insulation a frequent source of dripping and ceiling damage.
HVACCondensate drainageuPVC condensate pipe, fittings, insulation and cleaning teesAA - undrawn: generally 25/32 mm pipe, preliminary fall >=1:100; trap to unit pressure requirements and provide accessible cleaning points. Terminate through an approved indirect connection.mAll fourAvoids stagnant water and sewer odour entering the AC system.
HVACCondensate lift - substitutionLow-noise condensate pump with reservoir and alarmALTALT - undrawn: replaces gravity discharge locally only where falls cannot be achieved; typically 5-10 m lift class, selected to actual flow/head, with high-level AC shutdown.setAll four, where necessaryPumps add maintenance and should be limited to locations that need them.
HVACSupply and return ductsSealed sheet-metal ductwork, plenums and short flexible connectorsAA - undrawn: preliminary 0.6-0.8 mm sheet metal for small ducts, gauge to dimensions; protected metal indoors and suitable corrosion-resistant construction externally. Avoid long flexible-duct runs.m2All fourLow resistance and airtight joints reduce fan noise and wasted cooling.
HVAC
HVACAC grillesSupply diffusers, return grilles, dampers and removable filtersAA - undrawn: coordinated concealed/linear outlets; low face velocity, accessible filters and balancing dampers. Bedroom acoustic target approximately NR25, subject to acoustic design.noAll fourAvoids draughts over beds and provides maintainable filters.
HVACDrawing-indicated exhaust terminalsCeiling-mounted exhaust grillesDD: two exhaust vents per villa. A: preliminary 125-150 mm connections; locations, duct connections and performance unconfirmed. Additional terminals may be required for all enclosed WC/shower compartments.noAll fourTwo ceiling symbols do not prove adequate extraction for a three-bathroom villa.
HVACBathroom exhaust fansLow-noise EC inline/centrifugal fansAA - undrawn: preliminary 100-150 m³/h per main bathroom and 60-90 m³/h for maid bathroom; select at actual duct resistance. Allow separate branches for WC and shower compartments.noAll four; maid allowance A10/A11Removes moisture and odour while allowing fans to be maintained away from the guest's head.
HVACExhaust ductworkRigid corrosion-resistant ducts, dampers and external terminalsAA - undrawn: preliminary 125-160 mm main-bath ducts and 100-125 mm maid branches; backdraft dampers, cleaning access, weather louvres and insect screens. Fire dampers where the fire strategy requires them.mAll fourSalt-resistant terminals and proper discharge locations prevent corrosion and odour recirculation.
HVACFresh-air treatmentFiltered outdoor-air unit with active cooling/dehumidificationAA - undrawn: preliminary package range 120-180 m³/h for A09/A12 and 250-400 m³/h for A10/A11; final outside-air quantities based on occupancy and exhaust balance. ERV alone is not assumed to control humidity.setAll fourRecirculating split/VRF units do not supply fresh air; untreated outdoor air can overwhelm latent capacity.
HVACTransfer airAcoustic transfer grilles or door-transfer assembliesAA - undrawn: size for bathroom exhaust replacement air while maintaining privacy and low noise; coordinate with doors and partitions supplied elsewhere.noAll fourExtract fans need a deliberate replacement-air path.
HVACTemperature and humidity controlWired thermostats, humidity sensors and GRMS interfacesAA - undrawn: enquiry room target 24-25°C and approximately 50-60% RH; unoccupied setback retains dehumidification. Include condensate-fault and equipment-fault reporting.setAll fourSwitching all cooling off when a guest leaves can create damp finishes and odours.
4. PLUMBING - WATER DISTRIBUTION, HOT WATER AND SANITARY CONNECTIONS
PlumbingVilla cold-water entryMeter, strainer, isolating valve, PRV, gauge and union connectionsAA - undrawn: preliminary DN25 entry for A09/A12 and DN32 for A10/A11; target approximately 2.5-3 bar dynamic pressure at outlets, subject to selected rain showers and simultaneous demand.setAll fourStable balanced pressure is important when guests use baths and showers together.
PlumbingInternal hot/cold pipework - basePEX-a or multilayer potable-water pipe with proprietary fittingsAA - undrawn: preliminary OD16-20 mm outlet branches, OD25 mm bath feeds, OD25-40 mm distribution. Use a complete certified system rated for design pressure and hot-water temperature.mAll fourPolymer pipe avoids marine corrosion; minimise inaccessible fittings and keep one compatible fitting system.
PlumbingInternal pipework - substitutionHeat-fusion PP-R/PP-RCT pipe and fittingsALTALT - undrawn: replaces the internal PEX/multilayer system above; preliminary OD20-40 mm, PN20 quotation class at 20°C, with pressure derating checked at operating hot-water temperature.mAll fourFamiliar island installation method, provided fusion workmanship and expansion control are reliable.
PlumbingIsolation and balancingDZR brass/bronze valves, check valves, unions and manifold assembliesAA - undrawn: isolate each bathroom, heater and maintainable appliance; generally DN15-32. Materials must suit the treated RO water chemistry.noAll fourLow-alkalinity water can attack unsuitable brass; bathroom isolation avoids closing an entire villa.
PlumbingHot-water generation H1 - baseLocal air-source heat-pump water heater with storage and electric backupAA - undrawn: preliminary 200-300 L storage for A09/A12 and 400-500 L for A10/A11; approximately 3-5 and 6-10 kW thermal recovery respectively, with staged electric backup. Storage volume requires actual bath capacity and simultaneous-use checks.setAll fourReduces electricity demand compared with resistance-only storage and avoids long shore-to-villa hot-water runs.
PlumbingHot-water generation - substitutionLocal electric storage cylindersALTALT - undrawn: replaces H1; same verified storage duty, preliminary 3 kW element for small villas and staged 2 x 3 kW for larger villas. Recalculate feeder loads and recovery time.setAll fourSimple equipment and readily stocked spares, but higher island generation demand.
PlumbingHot-water generation - substitutionCentral/cluster heat-recovery or heat-pump plant with circulation networkALTALT - undrawn: replaces H1; price shared generation/storage plus insulated flow/return mains, villa isolation, balancing and local temperature control. Capacity and route lengths remain unknown.setAll four - shared and villa interfacesAttractive where an existing heat source and nearby hot-water network are available; long jetty circulation losses must be included.
PlumbingHot-water generation - substitutionSolar-thermal preheat, storage and auxiliary heating packageALTALT - undrawn: replaces H1 with a complete equivalent-duty package; preliminary collector allowance 3-4 m² for small villas and 6-8 m² for larger villas, subject to solar/yield and roof assessment. Auxiliary heating remains necessary.setAll fourSolar availability helps, but roof corrosion, storm restraint and cloudy-period recovery matter.
PlumbingCylinder safety accessoriesExpansion vessel, relief valves, inlet controls, tundish and drain panAA - undrawn: complete manufacturer-approved unvented-cylinder safety group; relief pipe sized to discharge calculation and routed visibly to a safe approved drain.setAll fourProtects guests and maintenance staff from uncontrolled hot-water discharge.
PlumbingHot-water hygiene and temperingThermostatic mixing valves, temperature gauges and sampling pointsAA - undrawn: design for storage >=60°C and hot distribution >=50°C before local mixing; preliminary shower/bath delivery 38-43°C, set by operator risk assessment. Apply a complete water-safety plan.setAll fourThese are adopted engineering benchmarks, not claimed Maldives statutory temperatures; see HSE temperature-control guidance.
PlumbingHot-water return, where neededSmall bronze/stainless circulation pump, return pipe and balancing valvesAA - conditional, undrawn: DN15-20 local return where pipe lengths cause unacceptable wait time; temperature-controlled circulation. Essential component of the central-system alternative.setPrimarily A10/A11; others if requiredLimits wasted desalinated water while waiting for a hot shower.
Plumbing
PlumbingBath connection kitsConcealed hot/cold connections, isolation, waste, overflow and trapDD: baths A09/A12: one; A10/A11: two. A: preliminary DN20 supplies and DN40/50 wastes; accessible traps and supplier-matched connections. Bath bodies and exposed fillers excluded from this purchase.setAll fourActual tub volume and fill rate govern heater sizing; concealed waste access prevents destructive repairs.
PlumbingWC/cistern connection kitsWater isolation, cistern connection and soil pan connectorDD: WC/cisterns A09/A12: one; A10/A11: three. A: DN15 cold supply and approximately 90/110 mm soil connection, matched to the selected carrier/cistern. Fixture assemblies excluded here.setAll fourKeeps MEP connections compatible with the already selected wall-hung system.
PlumbingLavatory connection kitsHot/cold tails, isolating valves, waste and trapDD: lavatories A09/A12: one; A10/A11: three. A: DN15 supplies, DN32/40 waste and accessible trap. Lavatory bodies and exposed taps excluded here.setAll fourUse the supplied count; the phrase "twin vanity" does not justify inventing additional basins.
PlumbingIndoor shower connectionsConcealed connections, isolation and supplier-matched valve interfacesDD: rain heads A09/A12: one; A10/A11: three; handsets respectively one and two. A: preliminary DN20 main-shower feeds, balanced hot/cold pressure and accessible concealed valves. Exposed fittings excluded here.setAll fourRain heads and handsets can share a mixer; head count is not automatically mixer count.
PlumbingHand-bidet backflow protectionDedicated break-tank/booster arrangement with suitable air gapDD: hand bidets A09/A12: one; A10/A11: three. A: category-5-equivalent protection adopted; preliminary 20-50 L packaged tank serving a dedicated bidet circuit, with pump sized to simultaneous use.setAll fourA hose reaching a WC requires more than a simple check valve under the adopted approach; see Water Regs UK guidance.
PlumbingOutdoor shower connectionsIsolatable water branches and trapped foul-drain connectionDD: one outdoor shower at A09/A10/A12; two at A11. A: DN15-20 cold supply base, hot supply only if selected; approximately DN50 trapped drainage. Shower bodies excluded here.setAll fourSoap-bearing shower water is collected as wastewater, including over the lagoon.
PlumbingWater-leak controlLeak sensors, controller and motorised isolation valveAA - undrawn: sensors beneath cylinder and vulnerable concealed assemblies; alarm to resort engineering, with coordinated automatic shutoff where appropriate.setAll fourEarly warning limits water loss and damage while a villa is vacant.
5. PLUMBING - SANITARY DRAINAGE AND FOUL SEWERAGE
PlumbingInternal waste branchesHDPE/PP sanitary drainage pipe, fittings and acoustic supportsAA - undrawn: generally DN40/50 basin, bath and shower wastes; larger combined branches by discharge-unit calculation. Preliminary falls around 1:40-1:60 where applicable, checked against the adopted BS EN 12056 design.mAll fourReliable falls, access and acoustic isolation prevent blockages and guest complaints.
PlumbingSoil branches and stacksWelded HDPE soil pipe, swept branches and access fittingsAA - undrawn: preliminary 110 mm OD main soil pipe; welded underdeck joints, cleaning access at changes of direction and stack bases. Verify hydraulic capacity and support spacing.mAll fourWelded plastic systems tolerate marine exposure without relying on corroding metal drain pipe.
PlumbingVent stacksUV-resistant HDPE/uPVC vent pipe and weather terminalsAA - undrawn: preliminary DN75-110 venting, with final sizes and discharge locations coordinated away from openings and fresh-air intakes. Air-admittance valves only as an approved supplement.mAll fourProper venting preserves trap seals and carries odour away from guest areas.
PlumbingFloor drainsTrapped drain bodies, removable baskets and compatible outlet fittingsAA - undrawn: generally DN50/75 outlets, approximately 50-75 mm water seals where selected system permits; accessible cleaning and trap replenishment where needed. Quantities require drainage layouts.noAll fourShallow floor-level changes do not prove that adequate traps fit; allow underfloor service depth.
PlumbingBeach-villa external sewerBuried uPVC/HDPE drain pipe, inspection fittings and chamber internalsAA - undrawn: preliminary 110/160 mm pipe to resort sewer; gravity assumed only after an invert survey. Civil chamber shells, excavation and concrete remain outside this materials list.mA09, A10High groundwater makes watertight joints and controlled infiltration important.
PlumbingOverwater sewage S1 - baseSealed duplex sewage lifting stationAA - undrawn: short gravity branches collect blackwater and greywater into an accessible sealed HDPE/GRP vessel; two duty/standby sewage pumps return flow to shore. Preliminary enquiry duty 1-2 L/s at 10-20 m head; approximately 500 L gross vessel for A12 and 1,000 L for A11, subject to bath-discharge and emergency-storage calculations.setA11, A12This is a practical expansion allowance where a shore pressure connection is possible; do not use a domestic behind-WC macerator as the whole-villa base.
PlumbingOverwater sewage - gravity substitutionContinuous gravity collector to a surveyed shore receiving pointALTALT - undrawn: replaces S1 and its pressure main where continuous fall is demonstrably available. Preliminary 110/160 mm collector; at 1:80, a 100 m run consumes 1.25 m of fall before connection losses and clearance.setA11, A12A long shallow walkway often cannot provide enough fall while maintaining marine clearance.
PlumbingOverwater sewage - vacuum substitutionVacuum interface chambers, vacuum mains and shared vacuum stationALTALT - undrawn: replaces S1 and its pressure network as a complete system. Conventional WCs drain by gravity into interface chambers; vacuum conveys sewage to a shore vessel, then sewage pumps transfer it to treatment. Preliminary PE100 SDR11 mains OD90-160 mm, supplier-designed.setA11, A12 - shared networkRequires interface valves, vacuum pumps, collection vessel, discharge pumps, controls and standby power-not merely a different pipe.
PlumbingVacuum-system design allowanceProprietary interface valves, monitoring and profiled pipe fittingsALTALT - part of vacuum substitution: approximately −0.5 to −0.6 bar operating pressure, with engineered saw-tooth profile and verified lift/friction budget. Final layout to URA and selected supplier requirements.setA11, A12 - vacuum alternativeURA publishes specific requirements: URA 2003:2021, PDF pp. 38-40.
Plumbing
PlumbingSewage valves and maintenance fittingsFull-bore isolation, non-return valves, dismantling joints and flushing connectionsAA - S1 base, undrawn: valve set on each pump discharge; accessible branch isolation, engineered air-release points and closed tanker/bypass connection where needed.setA11, A12Enables a pump or branch to be repaired without opening sewage piping over the lagoon.
PlumbingSewage station monitoringLevel controls, independent high-high alarm, local panel and telemetryAA - S1 base, undrawn: duty alternation, pump-fail alarm, dry-run protection and independently sensed high level; backup-supported alarm and resort standby supply. No emergency overflow to lagoon.setA11, A12Failures must reach engineering staff before wastewater backs up into guest bathrooms.
PlumbingSewage containment and accessSealed covers, vent system, removal guides and lifting accessoriesAA - undrawn: vessel and covers located/protected to verified flood and wave conditions; removal access from the walkway, adequate emergency usable volume and safe pump-out provision.setA11, A12A buried-style tank suspended beneath a deck still needs buoyancy, splash and maintenance assessment.
PlumbingResort treatment interfaceShore receiving connection, flow measurement and sampling facilitiesAA - undrawn: connect to an approved resort STP after checking hydraulic, organic and peak-flow capacity. Existing STP technology, capacity and spare capacity are unknown.setAll four - sharedConveyance to shore does not itself treat sewage.
PlumbingAdditional treatment, if requiredPackaged biological STP, disinfection and sludge-handling equipmentAA - conditional, undrawn: separate shared allowance for capacity extension; MBBR/SBR/MBR selection and m³/day rating require resort population, loads and effluent/reuse criteria. Include screening, equalisation, pumps, aeration, controls and sludge removal.setAll four - sharedPrevents an assumed per-villa septic tank or untreated lagoon outfall becoming the default.
PlumbingSand interceptionRemovable sediment baskets or small accessible sand trapsAA - undrawn: provide at outdoor shower collection points; preliminary 15-30 L removable sediment collection where suitable, connected to foul drainage.noAll fourSand can block traps and damage sewage pumps.
PlumbingGrease interceptionGrease separator and associated connectionsAA - conditional, undrawn: no villa grease interceptor in the base because no cooking kitchen is identified. Add an EN 1825-sized separator only if food preparation/washing scope is introduced.setAny villa with subsequently confirmed kitchenA minibar alone does not create a grease-interceptor requirement.
6. WATER SUPPLY SOURCE AND RESORT DISTRIBUTION
Water supply source and resort disWater-source interfaceConnection to resort treated freshwater networkAA - undrawn: existing central desalination and storage assumed as the first interface to investigate; source, quality, capacity and spare capacity unconfirmed. Additional shared plant below is conditional on that investigation.setAll four - sharedAvoids purchasing a desalination plant for each villa or duplicating existing resort equipment.
Water supply source and resort disDesalination capacity additionModular seawater RO skidsAA - conditional, undrawn: seawater membranes, high-pressure pump, pressure vessels, controls and energy recovery where suitable; preliminary operating pressure approximately 55-70 bar, with components rated above maximum design pressure. Capacity requires a resort water balance.setAll four - sharedModular plant and common membrane sizes help maintain production during island servicing.
Water supply source and resort dis
Water supply source and resort disPotable post-treatmentRemineralisation/pH correction, disinfection and monitoring equipmentAA - conditional, undrawn: stabilise RO permeate before distribution; provide controlled disinfection, conductivity, pH and residual monitoring, sampling taps and potable-contact components.setAll four - sharedUntreated low-mineral permeate can be corrosive; UV alone leaves no disinfectant residual in long distribution pipes.
Water supply source and resort disFreshwater storageCovered potable GRP/HDPE tanks with screened vents and level controlsAA - undrawn: preliminary usable storage allowance of five days' approved design demand, with maintainable compartments and turnover management; confirm existing storage and fire-reserve separation.setAll four - sharedThe URA 2026 as-built guideline, PDF p. 8 expressly asks for storage justification against a five-day requirement.
Water supply source and resort disDistribution pumpingDuty/standby variable-speed booster set and pressure vesselAA - undrawn: select flow and head from network modelling to maintain villa outlet pressures; include dry-run protection, gauges, non-return valves, isolation and telemetry.setAll four - sharedShore-side redundancy reduces the need for noisy guest-villa booster pumps.
Water supply source and resort disIsland and jetty water mainsPotable-certified PE100 pressure pipe and electrofusion/butt-fusion fittingsAA - undrawn: preliminary OD63-110 mm shared mains and OD32-40 mm villa branches; PN16 quotation basis with temperature/surge checks. Shade exposed pipes and provide accessible isolation and flushing points.mAll four; jetty sections A11/A12Welded polymer mains resist seawater exposure and accommodate engineered thermal movement.
Water supply source and resort disRainwater harvestingScreens, first-flush devices, covered tanks and separate distribution equipmentAA - conditional, undrawn: nonpotable landscape/cleaning use assumed; catchment suitability and storage from rainfall/yield analysis. Potable top-up through an air gap; no cross-connection to drinking-water pipes.setAll four - shared or clusteredReduces RO demand where suitable clean catchments exist; thatch or contaminated roofs need specific assessment.
Water supply source and resort disRoof/stormwater conveyanceRainwater drainage pipe, outlets and cleaning fittingsAA - undrawn: preliminary 75-110 mm branches only for enquiry; final sizing from roof catchments and design rainfall. Keep clean stormwater separate from foul sewage and pool backwash.mAll fourTropical rainfall can overwhelm drainage sized only from floor area.
Water supply source and resort disRO brine disposalPressure pipe, valves, monitoring and approved outfall fittingsAA - conditional, undrawn: material and diameter from plant reject flow and approved discharge design; outfall location, diffuser and environmental conditions remain unknown.setAll four - sharedBrine disposal is a separate engineered environmental interface, not a connection beneath a water villa.
7. PLUNGE POOLS AND SLIDE-SERVICE INTERFACES
Plunge pools and slidePool hydraulic enquiry basisIndividually sized circulation plant packageDD: areas A09 15.02 m², A11 approximately 35.4 m², A12 13.67 m². A: illustrative 1.2 m mean water depth gives approximately 18.0/42.5/16.4 m³ respectively. The −1200 level does not establish water depth or water-surface elevation.setA09, A11, A12Pump and filter selections below are provisional until pool sections, waterline and bather duty are issued.
Plunge pools and slideA10 pool allowanceProvisional pool plant packageDD: 38.20 m² is combined deck/pool information. A: obtain separate pool dimensions and sections; price an A11-scale provisional plant only as an explicitly adjustable allowance.setA10Treating 38.20 m² as pool area would fabricate the pool volume.
Plunge pools and slideCirculation pumpVariable-speed pool pump with integral strainer basketAA - undrawn: preliminary 6 m³/h at 10-15 m head for A09/A12; 12 m³/h at 10-15 m for A11 and provisional A10. Approximately 0.55-1.1 kW and 1.1-1.5 kW motor classes; verify pump curves and actual turnover requirement.noAll fourVariable speed reduces noise and energy; selection must include real pipe and filter resistance.
Plunge pools and slideFilter vesselCorrosion-resistant GRP sand/glass-media pressure filterAA - undrawn: preliminary 600 mm diameter for A09/A12, 750 mm for A11 and provisional A10; pressure rating typically >=2.5 bar, subject to pump shutoff pressure. Include valves, gauge and air release.noAll fourGRP avoids corroding steel vessels and uses familiar service parts.
Plunge pools and slideFilter mediaGraded silica sand or approved activated glass mediaAA - undrawn: grading, support layers and charge mass strictly to selected filter; quote by kg, including initial charge and separately identified spare allowance.kgAll fourIncorrect grading can cause poor filtration or media loss into pools.
Plunge pools and slideSurface collection P1 - baseOverflow fittings, balance-tank fittings and prefabricated balance tankAA - undrawn: overflow/infinity operation assumed solely for enquiry; preliminary 1-2 m³ tank for A09/A12 and 3-5 m³ for A11/provisional A10. Final volume includes displacement, drain-down and operating reserve.setAll fourThe drawings do not confirm an overflow edge or balance tank; space and elevations are major coordination items.
Plunge pools and slideSurface collection - substitutionSkimmers, equalisation connections and water-level controlALTALT - undrawn: replaces P1 where a skimmer pool is approved; omit the overflow balance tank and associated overflow collection equipment.setAll fourA valid lower-complexity alternative, but it changes the pool edge and operating waterline.
Plunge pools and slidePool circulation pipeworkPressure-rated uPVC pipe and solvent-weld fittingsAA - undrawn: preliminary DN50/63 for small pools and DN63/75 for larger pools; PN10/16 as selected, UV-protected outdoors. Include unions, isolation valves, swept fittings and independently supported pipework.mAll fourReadily serviceable pressure plastics suit chlorinated water and marine surroundings.
Plunge pools and slideInlets and suction outletsPool return fittings, certified suction covers and collection fittingsAA - undrawn: returns arranged to avoid dead zones; no single blockable suction outlet. Engineer multiple/unblockable suction arrangements and cover ratings for maximum possible flow.setAll fourEntrapment protection must be designed as a complete hydraulic arrangement.
Plunge pools and slideAutomatic chemical controlpH/disinfectant controller, probes, flow cell and dosing pumpsAA - undrawn: sodium-hypochlorite dosing plus separate pH correction as base; flow-proved interlock stops dosing when circulation fails. Include calibration and sampling accessories.setAll fourAutomated control supports consistent water quality when guest use varies.
Plunge pools and slideChlorination - substitutionSalt chlorinator with compatible controller and cellALTALT - undrawn: replaces hypochlorite dosing equipment only; retain pH control. Size output to pool volume, temperature and bather load; confirm every wetted component's salt compatibility.setAll fourReduced liquid-chlorine handling must be weighed against salt-related corrosion and wastewater salinity.
Plunge pools and slideChemical storageSeparate chemical-compatible PE containers and spill traysAA - undrawn: preliminary 20-50 L day containers for small pools, 50-100 L for larger pools, adjusted to consumption and delivery interval. Physically segregate incompatible chemicals and provide dedicated ventilation.setAll fourAcid and hypochlorite must not share containment or an unventilated electrical cupboard.
Plunge pools and slide
Plunge pools and slidePool underwater lightingPool-rated LED fittings, niches and integral cablesAA - undrawn: preliminary 12 V AC SELV, IP68 fittings, approximately 10-20 W each; one-two for small pools and two-four for larger pools, subject to lighting design.noAll fourLow-voltage pool-rated equipment and sealed construction suit a wet bare-foot environment.
Plunge pools and slidePool electrical packageSafety isolating transformer, control panel and protective devicesAA - undrawn: transformer outside prescribed pool zones; primary circuit protection, local isolation, pump protection, bonding and interlocks designed to the adopted IEC/BS pool requirements.setAll fourPool lighting and pump equipment require coordinated protection, not just waterproof fittings.
Plunge pools and slidePool temperature controlReversible pool heat pump/chiller with titanium exchangerAA - conditional, undrawn: no active heating/chilling included in the base. Quote optional approximately 10-15 kW thermal class for small pools and 15-25 kW for larger pools, subject to heat-balance calculation.setAll fourMaldives plunge pools may need cooling as well as occasional heating; shaded airflow and noise are critical.
Plunge pools and slideBackwash and pool-emptying connectionControlled waste pipe, holding/equalisation and dechlorination provisionsAA - undrawn: route to the approved resort wastewater disposal system after checking chlorine, salinity and peak flow; do not assume direct STP acceptance or lagoon discharge.setAll fourA short filter backwash can create a large instantaneous load on small sewage systems.
Plunge pools and slidePool plant locationAccessible equipment skid, isolators, vibration mounts and leak detectionAA - undrawn: individual dry service bay adjacent to the pool; verify suction conditions and maintenance removal clearances. Do not assume all equipment fits the 3.14 m² MEP room or A11's 5.68 m² service room.setAll fourPool equipment, hot-water storage, AC and electrical gear compete for very limited space.
Plunge pools and slideOverwater pool elevationsRaised/protected equipment connections and service accessDD: pool datum −1200, high tide −1500 for A11/A12. A: equipment elevation requires flood, surge and wave assessment; the 300 mm difference is not a safe freeboard specification.setA11, A12Pumps and electrical boxes must not be placed at pool datum simply because the plan shows it.
Plunge pools and slideSlide wetting servicesConditional pump, strainer, isolation and dedicated wetting pipeworkDD: one RC slide at A09; two at A11. A: no wetting system is confirmed. If required by the slide designer, quote a separate hydraulically designed package; discharge destination and safety interlocks require confirmation.setA09, A11An RC slide does not prove that a pump is required or that it discharges into the pool.
8. FIRE DETECTION, FIREFIGHTING AND EMERGENCY LIGHTING
Fire detection, firefighting and eVilla fire detectionAddressable optical smoke detectors and basesAA - undrawn: detectors in each sleeping room, including maid accommodation, and other rooms/circulation required by the fire strategy. EN 54-compatible system; final quantities and positions require a fire layout.noAll fourDetached accommodation still requires prompt detection and notification to resort staff.
Fire detection, firefighting and e
Fire detection, firefighting and eAlarm notificationSounders, visual alarms and interfacesAA - undrawn: bedroom alarm design target approximately 75 dBA at the bedhead with doors closed; accessible-room visual/tactile provisions as required. Final cause-and-effect and sound calculations by fire designer.setAll fourA corridor sounder may not wake a guest behind closed doors.
Fire detection, firefighting and eResort alarm connectionApproved fire-alarm loop/network interface and isolatorsAA - undrawn: monitored connection to the resort fire panel; fault isolation at villa branches. Any fibre/network interface must be approved for the fire system, rather than relying on the ordinary guest LAN.setAll fourEngineering/security staff need to identify the particular villa and maintain alarm service during network faults.
Fire detection, firefighting and eFire-alarm wiringFire-resistant cables, supports and weatherproof interfacesAA - undrawn: preliminary 2-core 1.5 mm² fire-resistant cable where appropriate to the selected system; final cable construction and circuit survivability to fire design.mAll fourExposed walkway runs need both environmental protection and dependable alarm transmission.
Fire detection, firefighting and ePortable extinguishersEN 3 extinguishers and protective cabinetsAA - undrawn: preliminary one 6 L water-mist extinguisher of suitable fire rating near each villa exit; additional 2 kg CO₂ unit at electrical plant where the risk assessment supports it. Final type/count by fire authority and operator.noAll fourAppropriate cabinets resist salt exposure; selection should consider training and guest-area use.
Fire detection, firefighting and eEmergency luminairesSelf-contained LED emergency fittingsAA - undrawn: preliminary three-hour battery duration, automatic testing and external IP65 construction; illuminate escape paths, changes of direction and relevant equipment. Photometric design target generally >=1 lux on escape-route centreline.noAll four and access walkwaysLighting remains available during generator transfer, local circuit faults and key-card shutdown.
Fire detection, firefighting and eEscape signageMaintained illuminated exit/direction signsAA - undrawn: signs and pictograms to the adopted fire strategy; provide directional continuity from water villa to the designated safe shore route. Quantities await the escape layout.noAll four; especially A11/A12The overwater walkway is part of the evacuation route.
Fire detection, firefighting and eFixed firefightingConditional sprinkler/hydrant distribution and control equipmentAA - conditional, undrawn: determine need through the approved resort fire strategy, construction type, fire-service access and water supply. Do not infer exemption solely because a villa is detached.setAll four - villa and shared interfacesA required fixed system can materially affect shore pumps, storage and jetty service capacity.
9. SERVICES ROUTING OVER WATER
Services routing over waterMain service corridorCoordinated accessible walkway service zoneDD: overwater setting; A12 walkway-to-room identified. A: services run from shore along/within accessible jetty supports, then branch to each villa. Actual route, length, clearances and support geometry are unissued.setA11, A12No direct seabed route or hidden embedded route is assumed.
Services routing over waterPower containmentCovered UV-resistant GRP cable ladder/tray or heavy-duty ductsAA - undrawn: preliminary 300-450 mm shared power tray width, sized by cable fill and thermal calculation; secured covers, drainage and accessible pulling/inspection positions. Electrical cable itself is listed in Section 1.mA11, A12GRP avoids rapidly corroding ordinary galvanised tray in lagoon splash zones.
Services routing over waterData containmentSeparate GRP tray or HDPE ductsAA - undrawn: preliminary 100-150 mm tray or 50-63 mm ducts; physical separation/barrier from power, with one spare duct where practicable. Final spacing to EMC and containment design.mA11, A12Separate accessible routes simplify upgrades and fault finding.
Services routing over water
Services routing over waterFixings and interfaces316L fasteners, suitable GRP brackets and isolation washersAA - undrawn: corrosion-compatible combinations; isolate dissimilar metals and prevent crevices where practical. Higher-alloy/nonmetallic components where exposure warrants.setA11, A12"Stainless" is not sufficient specification for every wet chloride location.
Services routing over waterThermal movementEngineered pipe loops, sliding supports and anchor fittingsAA - undrawn: allow PE movement using supplier coefficients; illustrative 30 m pipe at 30°C temperature change can move about 180 mm at 0.2 mm/m/°C. Do not rigidly clamp an entire jetty run.setA11, A12Sun exposure produces significant movement even when the supporting walkway is fixed.
Services routing over waterStructural movement interfacesFlexible service loops and approved movement couplingsAA - undrawn: accommodate jetty joints, settlement and villa interfaces; cable bend radius, pipe pressure rating and fatigue duty govern the detail. Ordinary flexible hose is not the permanent sewage-main base.setA11, A12Prevents cracked fittings and pulled cable terminations at independently moving structures.
Services routing over waterShore/villa isolationAccessible power disconnects, water/sewer isolation and labelsAA - undrawn: isolate each branch without interrupting adjacent villas; arrange valves, meters and junctions where technicians can work from a safe access position.setA11, A12Allows occupied-villa maintenance and contains the consequences of a single failure.
Services routing over water
Services routing over waterService identificationUV-resistant labels, engraved tags, route markers and valve numberingAA - undrawn: identify both ends, branch points and isolation locations; coordinate with as-built drawings and resort maintenance numbering.setA11, A12Clear identification speeds repairs when replacement staff or outside contractors arrive by boat.
Services routing over waterMaintenance access fittingsRemovable containment covers, access-box hardware and lifting provisionsAA - undrawn: accessible cable joints, valves and pump removal points; sizes matched to equipment replacement. Walkway structure and architectural access panels remain coordinated with their separate packages.setA11, A12Equipment must be replaceable without dismantling large areas of finished guest walkway.
10. NORMAL MALDIVES RESORT PRACTICE - FOUR MAJOR DECISIONS
Normal Maldives resort practiceAC typeConcealed ducted DX split or villa-scale VRF/mini-VRFAA - KV2 system unknown: ducted splits suit individual small villas; mini-VRF suits several independently controlled rooms. Enquiry base: split for A09/A12, mini-VRF for A10/A11. These are established available approaches, not evidence of KV2's installed system.setAll fourMaldives contractors document split/mini-VRF/VRF resort installations; see ProAc resort projects. Concealed indoor equipment suits the ID intent.
Normal Maldives resort practiceHot-water typeHeat-recovery/heat-pump storage, solar-assisted storage or local electric storageAA - KV2 system unknown: there is no single universal arrangement. Central/cluster generation is attractive with nearby recovered heat; local storage avoids long circulation mains. Enquiry base is local heat-pump storage, with the listed substitutions.setAll fourActual Maldives projects include heat-pump conversion at Four Seasons Kuda Huraa, report p. 20 and solar hot water at Amari villas.
Normal Maldives resort practiceSewage from water villasShort gravity collection followed by gravity, pressure or vacuum conveyance to shoreAA - KV2 network unknown: select against actual jetty levels and the receiving network. Base is sealed duplex pressure lifting; vacuum is a complete network alternative; gravity is preferred only where surveyed falls work.setA11, A12Vacuum is recognised in URA's dedicated design guideline. None of these systems justifies untreated discharge beneath a villa.
Normal Maldives resort practicePool plant locationIndividual nearby service bay, with shared access where practicableAA - KV2 location unknown: practical enquiry arrangement is accessible local plant close to each pool. For water villas, use a dry protected bay/platform above verified marine design levels; below-deck placement is acceptable only if the complete access and flood design works.setAll fourShort pipe runs help hydraulics, but guest noise, chemical segregation and replacement access govern the final location. This is an engineering recommendation, not a confirmed drawing detail.
11. URA APPROVALS, SUBMISSIONS AND COMPLETION RECORDS
URA approvals, submissions and comPanel/SLD approvalENE01 application and electrical design packageAA - submission scope; drawings absent: triggered by the assumed >=63 A incomers. Submit SLD, A4 load calculations, phase balance, feeder/cable/protection schedules, owner identification, property documents, engineer appointment and applicable transformer/generator details. Include previous approvals for amendments.setAll four and affected shared panelsEnergy Act 18/2021; 2023 SLD guideline; 2024/G-14. Use the current ENE01 form, PDF pp. 1-2.
URA approvals, submissions and comPower-system designENE05 application and resort power-system reportAA - submission scope; network unknown: submit new/amended generation and distribution design, demand assessment, source capacities, protection/earthing philosophy, SLDs, layouts and equipment particulars. Establish the existing approved system first.setAll four - sharedEnergy Act 18/2021 and 2026/R-57; ENE05 v2 identifies the owner, system location and responsible licensed engineer.
URA approvals, submissions and comGenerator approval and operationENE05/ENE01 interfaces, registration and applicable operating authorisationAA - conditional on generator works: submit generator rating/data, installation, fuel/exhaust/ventilation details, switching/protection, tested revenue-grade metering and emergency-load arrangements. Obtain the applicable operating licence/permit before operation; confirm ENE07 applicability for non-utility self-generation.setShared power facilityOLR Energy 2023/R-78 and amendments; Standby Generator Guideline 2024/G-7. Current URA energy forms include ENE07 and facility/operator applications.
URA approvals, submissions and comSolar interconnectionNet-metering application/agreement where applicable; ENE05/SLD amendmentsAA - conditional on PV: submit array/inverter data, protection, metering, source-control philosophy and connection design. Net metering applies where the relevant utility interconnection exists; it is not automatically the arrangement for a private island microgrid.setShared power facilityNet Metering Regulation 2020/R-46; confirm the actual electrical relationship with the licensed network/operator.
URA approvals, submissions and comRenewable import reliefENE02 duty-exemption applicationAA - conditional on eligible imports: submit product descriptions, technical literature and import/consignment documents required by the current form. This does not replace electrical design approval.setShared PV/renewable scopeSeparate commercial/import process; see the URA ENE02 form through the current URA form register if the download has changed.
URA approvals, submissions and comCable/meter product acceptanceENE04 / ENE03, where requiredAA - conditional on product approval status: confirm whether proposed imported cable and metering products already have accepted approvals; submit manufacturer data and applicable test certificates for new approval applications.setAll four and shared infrastructureThese forms are listed separately in the URA energy approval register.
URA approvals, submissions and comWater-system approvalWTR03 and relevant system annexesAA - submission scope; water system absent: submit concept approval where required, EIA decision statement, design report, A3 layouts, source/demand/storage calculations, RO process/P&ID, distribution hydraulics, intake/brine details, equipment catalogues and supporting structural/electrical designs.setAll four - resort systemWater and Sewerage Act 8/2020, 2021/R-23 and applicable 2022/R-90 connection provisions. Requirements appear in the WTR03 system annexes.
URA approvals, submissions and comRO registration and operating routeFacility registration/operator authorisation; WTR04 only where applicableAA - conditional on plant scope: identify whether the plant supplies the resort network or is genuinely standalone. Submit plant/site/capacity particulars, approval references and the operating documentation required for the applicable category.setShared water facilityDo not automatically classify a networked resort RO as standalone. URA's water approval register distinguishes WTR04 from facility/operator applications.
URA approvals, submissions and com
URA approvals, submissions and com
URA approvals, submissions and comWaste-system design approvalWST03AA - conditional on new/amended waste-system design: submit waste-generation basis, collection/transfer arrangements, facility layout, storage/treatment capacities, equipment data, drainage, fire and environmental controls.setResort-wideSeparate from WST02: URA publishes a distinct WST03 design-approval form.
URA approvals, submissions and comExisting utility upgradesGEN04, where applicable, plus sector amendmentsAA - existing approvals unknown: submit existing approved arrangement, proposed change, capacity justification and revised drawings; coordinate shutdown and connection arrangements with the resort operator.setAll four - shared interfacesExtension of an operating resort must be related to its existing authorisations; GEN04 is listed by URA.
URA approvals, submissions and comProfessional endorsementLicensed engineering drawings, calculations and signed submission sheetsAA - required design service; absent from package: commission the appropriate licensed disciplines; provide engineer name, licence number and signature on submitted drawings/SLDs, with coordinated addresses, numbering and revisions.setAll four and shared systemsPower-sheet endorsement is explicit in the URA SLD guideline, PDF p. 2. This enquiry schedule is not that endorsement.
URA approvals, submissions and comEmergency and fire coordinationEscape-lighting layouts, emergency-power schedule and fire-authority submissionAA - undrawn: include escape routes and emergency lighting/power layouts with applicable generator/panel submission. Obtain building/fire acceptance separately; coordinate detector coverage, extinguishers and any fixed firefighting system.setAll four and walkwaysURA electrical approval does not establish complete building fire compliance.
URA approvals, submissions and comCompletion documentationAs-built drawings, asset schedules, test records and O&M manualsAA - completion deliverable: prepare sector reports and separate annexes in the 2026 URA format; include CAD/PDF routes, pipe/cable sizes, equipment IDs, pump duties, settings, photographs, commissioning results, water-quality records, spares and maintenance instructions.setAll four and shared systemsFollow the URA 2026 as-built guideline; record missing information explicitly and retain traceable operating/licensing records.
THERE ARE NO MEP DRAWINGS IN THE KV2 PACKAGE. No electrical layout, no single line diagram, no plumbing or drainage, no HVAC, no pool plant. This is a design-intent enquiry schedule built from the sanitary fixtures, ceiling fixtures and room areas that ARE on the interior-design drawings, plus normal Maldives resort practice and the URA regulatory requirements that govern utility work here. Quantities are deliberately blank - they cannot be established without a services design. Use this for budget rates, lead times and to scope the MEP consultant's brief.
STATUS KEY D = confirmed by the drawing information issued. A = assumed design intent or preliminary specification, absent from the package. ALT = a priced alternative to the item above it, not an addition.
TERRABUILD GLOBAL | sales@terrabuildglobal.com | terrabuildglobal.comWhatsApp / WeChat +86 188 2649 1416 | TBG-KV2-MEP-001 Rev 01
Room D076, Shop 101, No. 14, Longdong Trade Street, Tianhe District, Guangzhou City, China | Registered in the People's Republic of China
FormTrigger / systemWhat URA requiresGoverning instrumentStatusOwner
ENE01Electrical distribution panel, main incomer >= 63 APanel design approval: single line diagram + load calculation + owner ID + property registry + project-award letter. MV panels add transformer and switchgear documents. Submit to secretariat@ura.gov.mv.Energy Act 18/2021; SLD & Load Calculation Guideline 2023; Electrical Sector Design Approval Guideline 2024/G-14NOT STARTED
ENE05Power system design (generation / distribution works)Power system design approval for the resort distribution feeding the villas.Energy Act 18/2021; General Regulation for Energy Services 2026/R-57NOT STARTED
ENE05 + OLRStandby or prime generatorRegister the generator and obtain an operating licence. Revenue-grade kWh metering. An emergency-lighting floorplan must accompany the panel submission wherever standby provision exists.OLR Energy 2023/R-78 (+2023/R-148, 2025/R-65); Standby Generator Guideline 2024/G-7NOT STARTED
Net meteringGrid-tied solar PVNet-metering agreement with the utility. The panel/SLD must show the PV source.Net Metering Regulation 2020/R-46; 2026/R-57IF APPLICABLE
ENE02
WTR03
SWG01
WST02
GEN01
As-built
ALL
THE NUMERIC RULES URA ENFORCES ON A PANEL SUBMISSION (SLD & Load Calculation Guideline 2023)
- Connected load must not exceed 80% of the incomer trip rating.
- Busbar rating must be at least 125% of the incomer.
- CT primary rating must not exceed the trip rating.
- Four-pole breakers are required wherever there is more than one source.
- Overcurrent AND earth-leakage relays are both mandatory.
- The load calculation must be presented in URA's format: quantity x watts x load factor x diversity factor, VA = W / power factor, feeder amps at 230/400 V 50 Hz.
URA publishes no Maldives wiring code and no plumbing code. Detailed technical design therefore imports international practice - IEC / BS 7671 for wiring at 230/400 V 50 Hz. Building-side fire, egress and sanitary provision sits with the building authority, not URA. Licensing is part of MEP scope here: gensets, desalination plants and waste facilities need operating licences, not just design approval. No utility design is complete until the licence path is stated.
TERRABUILD GLOBAL | sales@terrabuildglobal.com | terrabuildglobal.comWhatsApp / WeChat +86 188 2649 1416 | TBG-KV2-MEP-001 Rev 01
Room D076, Shop 101, No. 14, Longdong Trade Street, Tianhe District, Guangzhou City, China | Registered in the People's Republic of China
BASIS OF THE MEP SCHEDULE
WHAT THE DRAWINGS GIVE US
Sanitary fixturesCounted off the plans and 1:25 bathroom elevations. Per villa A09/A10/A11/A12: freestanding bath tub 1/2/2/1, wall hung WC with concealed cistern 1/3/3/1, countertop lavatory 1/3/3/1, rain shower 1/3/3/1, handheld shower 1/2/2/1, hand bidet 1/3/3/1, outdoor deck shower 1/1/2/1, vanity mirror with integrated lights 1/3/3/1.
Ceiling and electricalReflected ceiling plans give four spotlight types (1W, 3W, 5W 3000K and 10W white), a dimmable 2800K LED striplight in perimeter coves running 18-62 m per villa, two ceiling-mounted exhaust vents per villa, wall lamps, wall-mounted TVs and socket outlets on the bedroom elevations.
Plant spaceA dedicated MEP room of 3.14 m2 in A09, A10 and A12; a service room of 5.68 m2 in A11. That is the only space allocated for services in the whole set.
PoolsEvery villa has a pool at -1200 below its finished floor level. A09 15.02 m2, A11 approx 35.40 m2, A12 13.67 m2, A10 within a combined 38.20 m2 deck/pool figure.
Water villas
What is absent
THE FOUR DECISIONS THAT DRIVE THIS PACKAGE
Air conditioning
Hot water
Foul drainage from the water villas
Pool plant location
REGULATORY POSITION
Utility work in the Maldives is regulated by URA - the Utility Regulatory Authority. Design approval, operator licensing and as-built submission are part of MEP scope here, not an afterthought. Eleven approval items apply to this scope and are set out on the URA Approvals sheet. Every drawing and single line diagram must carry the name, licence number and signature of a URA-licensed engineer.
The most commonly missed point: the panel submission (ENE01) is triggered at a main incomer of 63 A or above, and URA enforces specific numeric rules on it - connected load at or below 80% of the incomer trip, busbar at least 125% of the incomer, CT primary not exceeding the trip rating, four-pole breakers with multiple sources, and both overcurrent and earth-leakage relays. A design that ignores these will be rejected.
WHAT THIS SCHEDULE CANNOT TELL YOU
- Quantities. Cable lengths, pipe runs, fixture counts beyond the sanitary ware, equipment capacities and plant sizes all need a services design. None exists.
- Loads. There is no load schedule, so the incomer size, the submain to each villa and therefore the ENE01 trigger cannot be confirmed.
- The four decisions above. Until AC type, hot water type, water-villa foul drainage and pool plant location are settled, large parts of this schedule are placeholders.
- Anything about the resort-wide infrastructure - desalination capacity, generator sizing, sewage treatment, the walkway services corridor - which sits outside the villa drawings entirely.
SOURCES
- URA (Utility Regulatory Authority) published corpus, indexed 2026-08-14: Energy Act 18/2021; General Regulation for Energy Services 2026/R-57; SLD & Load Calculation Guideline 2023; Electrical Sector Design Approval Guideline 2024/G-14; Standby Generator Guideline 2024/G-7; Net Metering Regulation 2020/R-46.
- Water and Sewerage Act 8/2020 (+4/2022, 11/2025); General Regulation 2021/R-23 (+2023/R-54); House Connection Regulation 2022/R-90; Water Resources Conservation and Management 2021/R-22; Dewatering 2021/R-20.
- Waste Management Act 24/2022; Waste Management Regulation 2013/R-58 and its five amendments; Registration & Billing 2023/R-115; Design Guidelines for Waste Management Facilities 2023.
- Guideline for As-built Documentation 2026 (all utility sectors).
- IEC / BS 7671 at 230/400 V 50 Hz for detailed wiring design - URA publishes no Maldives wiring or plumbing code.